The statutory route into quantity surveying in Nigeria, examined for registration by the Board and practised under the Nigerian Institute of Quantity Surveyors. The track follows the work itself rather than the textbook definitions: order of cost estimates and floor-area rates, elemental cost plans, taking off and billing against a standard method of measurement, rate build-up from labour, plant and material, interim valuations with retention and fluctuations, variations and claims, the final account, and the earned-value and cash-flow reporting that keeps a live project honest. Nigerian conditions of contract and the local procurement scene are treated as the working environment, not as footnotes.

Sample lesson
Estimating Before the Design Exists
Orders of cost and elemental cost planning, the discipline a standard method imposes on taking off and billing, rate build-up, and the cost data that makes the next estimate better.
The examiner is testing whether you can put a number on a building that does not exist yet, and defend it. That means three things in every answer: the basis (what is included and excluded), the rate's source and date, and an explicit statement of accuracy. A candidate who writes '₦1.5bn' has answered nothing; one who writes '₦1.5bn on a gross-floor-area rate of ₦420,000/m² at 2025 price levels, excluding external works, foundations pending soil data, and within ±20% until the structural frame is designed' has produced a document a client can act on. The second thing the paper marks is arithmetic discipline: area to rate, deductions, waste, and the difference between net and gross quantities. The measurement items look simple and are where marks are lost — a candidate who bills a wall in square metres without stating its thickness, or who forgets that a floor-area rate must be multiplied by the correct area definition, has described estimating rather than done it.
The floor-area method is the workhorse at a feasibility stage: gross internal area times a rate for a building of the same type, quality and storey count, then adjustments for the things the average rate cannot know — a basement, a long span, an unusually heavy façade, site conditions that will need piling, and the services density of a laboratory or a hospital. The cubic method is better where volume drives cost (a warehouse, a car park, a hall with a high roof), because it prices the envelope that a floor rate silently assumes. Both are approximations of a cost per unit of provision, so the unit of comparison must be the same as the source data's: a rate struck for a three-storey reinforced-concrete frame in a city does not describe a single-storey steel building in a remote location. A cost plan replaces the single rate with the building's own elements — substructure, frame, roof, finishes, fittings, services, works outside the envelope, preliminaries and risk — each expressed per m² or as a percentage of the total, and it is the instrument by which a design is held to a budget. The moment it earns its keep is at concept: the plan sets a limit per element, the architect's design is measured against it, and the quantity surveyor reports the variance while there is still time to move a wall instead of deleting a window. Cost limits are meaningless without a stated allowance for what is not yet designed; and every element figure should record whether it is net of the provisional sums that sit outside it, so two people reading the plan cannot add the same money twice.
Read-only preview. Quizzes and progress tracking start in the full course.
What a mock looks like
QSRBN Part A-Style Mock
45 minutes total, with sections timed individually.
- Construction Economics & Estimating11 min
- Measurement & Billing11 min
- Contract Practice & Valuation11 min
- Cost Control, Procurement & Ethics12 min
A bill item is 120 m² at a rate of ₦12,000 per m². At the first interim valuation 60% of the item is complete and the contract provides for 10% retention. What amount is certified for payment on this item, net of retention?
- ₦777,600
- ₦864,000
- ₦1,296,000
- ₦86,400